Industrial and Production Plant
Direct reduction plant at the SALCOS® site, Salzgitter
Reduced CO2 emissions through the conversion of steel production to a hydrogen-based process
Salzgitter Flachstahl GmbH (SZFG) supports Germany's international commitment to reduce greenhouse gas emissions. To this end, the company has set up the transformative SALCOS® "Salzgitter Low CO2 Steel-Making" program. As part of the transformation, the previous carbon-based steel production process will be gradually replaced by a new hydrogen-based method.
With the completion of the last stage in 2033, current direct CO2 emissions of around 8 million tons per year can be cut by up to 95 %. This means that the Salzgitter site alone could reduce Germany's CO2 emissions by around 1 %.
All SALCOS® sub-projects are being implemented within Salzgitter Flachstahl GmbH premises. The experts at Drees & Sommer are coordinating the planning and construction participants, ensuring the planning and construction process runs smoothly, and keeping an eye on the costs and deadlines of the sub-projects.
The direct reduction plant is one of our Top Projects — a category reserved for work we are especially proud of. These projects have not only delivered exceptional value for our clients, but have also shaped us as a company.
Why the SALCOS® direct reduction plant is one of our Top Projects:
- Groundbreaking: a lighthouse project for the transformation of the steel industry toward green steel production
- Highly complex: challenging conversion of an integrated steel mill during ongoing operation
- Single source: comprehensive project support encompassing a wide range of in-house services
Added values
- Optimization and support for construction and assembly processes
- Optimization of construction scheduling
- Supporting the principal in their role
- Identification, coordination and control of collision avoidance in the 3D model
- Preparation of crane concepts and construction site equipment planning
Services
- Installation and construction site planning including installation coordination
- BIM management (DRP and EAF)
- Subproject management and project management for cost groups 300 to 500
- Risk management
- Site supervision
- Construction logistics planning and control
- EPCM Return material loading
- Interface management – construction/plant/logistics
Impressions
© Salzgitter AG
© Salzgitter AG
© Salzgitter AG