Welcome to our Shared Content Center! This is where you will find news, current developments and interesting stories about our company and the topics that keep driving us forward. We share information here, about our projects, innovations and events, in a variety of formats, such as blog posts, press releases and files. If you want to keep yourself updated, you're in the right place. 

News

Latest First: In our news articles, you’ll find everything we currently have to report.

Press

10 Years of Phasing out Nuclear Power: Dismantling Nuclear Power Plants

© Drees & Sommer SE
Green meadow instead of reactor dome: last German nuclear power plant will go offline in 2022.

Stuttgart, Germany, March 11, 2021. Ten years ago today, Japan was hit by a severe undersea quake. A tsunami rolled toward the coast at 800 kilometers per hour, with two 15-meter-high flood waves hitting the Fukushima One nuclear power plant and flooding its reactor blocks. The nuclear meltdown had devastating consequences for the environment. It also affected German energy policy: it was decided to phase out nuclear power, so next year the last German nuclear power plants will go offline. However, dismantling them is extremely costly. Because of this, Drees & Sommer SE, an international consulting company specializing in construction and real estate, is using a digital power plant twin to plan the dismantlement procedure.

A large number of laws, regulations and directives apply even to normal buildings. In Germany, these often vary from one federal state to another. In the case of nuclear power plants, there are also reusable materials, highly radioactive components and hazardous waste, the disposal of which must be carefully planned. Overall, several decades can pass between the time the power plant is taken offline and the end of decommissioning. The first German nuclear power plant in Kahl am Main near Aschaffenburg, for example, was operational for 25 years until it was shut down in 1985.

Demolition then took longer than the period of operation and, at EUR 150 million, cost even more than construction. Decommissioning the Stade nuclear power plant, the first reactor to be taken offline as a result of the nuclear phase-out approved by the Red-Green government at the time, was somewhat faster, but still took 13 years.

A digital twin helps with power plant demolition

The reason for the long period between shut-down and complete decommissioning is that many radiation-contaminated components have to be dismantled and cleaned at great expense before they can be disposed of. And a nuclear power plant is big: at the Greifswald nuclear power plant, for example, 1.8 million metric tons of building material must be disposed of. The complex planning of shutdown and dismantling can be made easier by using a cutting-edge digital tool: Building Information Modeling (in short: BIM). This refers to a method of networked collaboration that brings together all relevant data in a model, enabling processes, products and participants to be digitally networked. In specific terms, this means that before the first stone is turned during dismantling, a digital model of the actual power plant and the technical equipment is constructed. ‘This model has long since included not just the geometric data, but also all the information on materials and fire control systems, for example,’ explained Peter Liebsch, Associate Partner at Drees & Sommer Group and expert for digital planning. This creates a digital twin with a depth of information down to the smallest detail.

High level of safety despite radiation contamination

All scheduling, (de)construction, material flow and logistics processes can then be simulated with the aid of this digital building model. Ideally, the model would be cloud-based, making it accessible to all project participants from any location. When BIM is used in planning the dismantling of a nuclear power plant, the entire power plant is first scanned with the appropriate equipment. ‘In areas that are inaccessible due to high radiation contamination, robots are used for this purpose. It is also possible to make measurements of things such as the contamination of individual areas with radioactivity, asbestos or other hazardous materials,’ Peter Liebsch continued. This method creates a faithful, virtual model of the power plant, including a contaminant register, which accurately represents the actual condition down to a few centimeters. In this model, the team plans the dismantling process and logistics, and adds critical information to it.

This procedure may sound time-consuming at first, because enhancing the digital twin with all the necessary data naturally increases the time and effort initially required at the preparation stage. But it does mean that discrepancies are not first noticed during the dismantling process and at the construction logistics stage, where they could result in expensive delays. Instead, the digital model is used to check for conflicts and consistency, ensuring that the deconstruction process runs smoothly. In addition, several variants of the demolition planning can be run through the BIM model and compared with each other, both with regard to scheduling and costs.

All the cogs mesh together

BIM also brings several major advantages in relation to the practical processes involved in dismantling. Firstly, occupational safety is increased for every individual who will later work on the plant. After all, you can take a virtual walk through the power plant and, by doing so, protect yourself from unpleasant surprises in reality. In the interests of occupational health and safety together with radiation protection, this reduces the time-consuming procedure of passing through air-lock systems to get to the hot zone. Secondly, the dimensions generated from the BIM model can be used for precisely scheduled demolition planning. They are also useful for detailed tendering, work preparation and logistics, including complete verification management for surveyors and official bodies. The dismantling process is much faster as a result, because all the cogs mesh together. And then it will not be long before nuclear energy in Germany really is a thing of the past – and in those places where reactor domes still tower up today, only green meadows will remain.

More News

Blog posts

Get new insights into the work of Drees & Sommer and learn more about current topics, projects and trends.

Press

10 Years of Phasing out Nuclear Power: Dismantling Nuclear Power Plants

© Drees & Sommer SE
Green meadow instead of reactor dome: last German nuclear power plant will go offline in 2022.

Stuttgart, Germany, March 11, 2021. Ten years ago today, Japan was hit by a severe undersea quake. A tsunami rolled toward the coast at 800 kilometers per hour, with two 15-meter-high flood waves hitting the Fukushima One nuclear power plant and flooding its reactor blocks. The nuclear meltdown had devastating consequences for the environment. It also affected German energy policy: it was decided to phase out nuclear power, so next year the last German nuclear power plants will go offline. However, dismantling them is extremely costly. Because of this, Drees & Sommer SE, an international consulting company specializing in construction and real estate, is using a digital power plant twin to plan the dismantlement procedure.

A large number of laws, regulations and directives apply even to normal buildings. In Germany, these often vary from one federal state to another. In the case of nuclear power plants, there are also reusable materials, highly radioactive components and hazardous waste, the disposal of which must be carefully planned. Overall, several decades can pass between the time the power plant is taken offline and the end of decommissioning. The first German nuclear power plant in Kahl am Main near Aschaffenburg, for example, was operational for 25 years until it was shut down in 1985.

Demolition then took longer than the period of operation and, at EUR 150 million, cost even more than construction. Decommissioning the Stade nuclear power plant, the first reactor to be taken offline as a result of the nuclear phase-out approved by the Red-Green government at the time, was somewhat faster, but still took 13 years.

A digital twin helps with power plant demolition

The reason for the long period between shut-down and complete decommissioning is that many radiation-contaminated components have to be dismantled and cleaned at great expense before they can be disposed of. And a nuclear power plant is big: at the Greifswald nuclear power plant, for example, 1.8 million metric tons of building material must be disposed of. The complex planning of shutdown and dismantling can be made easier by using a cutting-edge digital tool: Building Information Modeling (in short: BIM). This refers to a method of networked collaboration that brings together all relevant data in a model, enabling processes, products and participants to be digitally networked. In specific terms, this means that before the first stone is turned during dismantling, a digital model of the actual power plant and the technical equipment is constructed. ‘This model has long since included not just the geometric data, but also all the information on materials and fire control systems, for example,’ explained Peter Liebsch, Associate Partner at Drees & Sommer Group and expert for digital planning. This creates a digital twin with a depth of information down to the smallest detail.

High level of safety despite radiation contamination

All scheduling, (de)construction, material flow and logistics processes can then be simulated with the aid of this digital building model. Ideally, the model would be cloud-based, making it accessible to all project participants from any location. When BIM is used in planning the dismantling of a nuclear power plant, the entire power plant is first scanned with the appropriate equipment. ‘In areas that are inaccessible due to high radiation contamination, robots are used for this purpose. It is also possible to make measurements of things such as the contamination of individual areas with radioactivity, asbestos or other hazardous materials,’ Peter Liebsch continued. This method creates a faithful, virtual model of the power plant, including a contaminant register, which accurately represents the actual condition down to a few centimeters. In this model, the team plans the dismantling process and logistics, and adds critical information to it.

This procedure may sound time-consuming at first, because enhancing the digital twin with all the necessary data naturally increases the time and effort initially required at the preparation stage. But it does mean that discrepancies are not first noticed during the dismantling process and at the construction logistics stage, where they could result in expensive delays. Instead, the digital model is used to check for conflicts and consistency, ensuring that the deconstruction process runs smoothly. In addition, several variants of the demolition planning can be run through the BIM model and compared with each other, both with regard to scheduling and costs.

All the cogs mesh together

BIM also brings several major advantages in relation to the practical processes involved in dismantling. Firstly, occupational safety is increased for every individual who will later work on the plant. After all, you can take a virtual walk through the power plant and, by doing so, protect yourself from unpleasant surprises in reality. In the interests of occupational health and safety together with radiation protection, this reduces the time-consuming procedure of passing through air-lock systems to get to the hot zone. Secondly, the dimensions generated from the BIM model can be used for precisely scheduled demolition planning. They are also useful for detailed tendering, work preparation and logistics, including complete verification management for surveyors and official bodies. The dismantling process is much faster as a result, because all the cogs mesh together. And then it will not be long before nuclear energy in Germany really is a thing of the past – and in those places where reactor domes still tower up today, only green meadows will remain.

Dreso-Blog

Press Releases

Find out more about the latest developments and exciting news from our company in our current press releases.

Press

10 Years of Phasing out Nuclear Power: Dismantling Nuclear Power Plants

© Drees & Sommer SE
Green meadow instead of reactor dome: last German nuclear power plant will go offline in 2022.

Stuttgart, Germany, March 11, 2021. Ten years ago today, Japan was hit by a severe undersea quake. A tsunami rolled toward the coast at 800 kilometers per hour, with two 15-meter-high flood waves hitting the Fukushima One nuclear power plant and flooding its reactor blocks. The nuclear meltdown had devastating consequences for the environment. It also affected German energy policy: it was decided to phase out nuclear power, so next year the last German nuclear power plants will go offline. However, dismantling them is extremely costly. Because of this, Drees & Sommer SE, an international consulting company specializing in construction and real estate, is using a digital power plant twin to plan the dismantlement procedure.

A large number of laws, regulations and directives apply even to normal buildings. In Germany, these often vary from one federal state to another. In the case of nuclear power plants, there are also reusable materials, highly radioactive components and hazardous waste, the disposal of which must be carefully planned. Overall, several decades can pass between the time the power plant is taken offline and the end of decommissioning. The first German nuclear power plant in Kahl am Main near Aschaffenburg, for example, was operational for 25 years until it was shut down in 1985.

Demolition then took longer than the period of operation and, at EUR 150 million, cost even more than construction. Decommissioning the Stade nuclear power plant, the first reactor to be taken offline as a result of the nuclear phase-out approved by the Red-Green government at the time, was somewhat faster, but still took 13 years.

A digital twin helps with power plant demolition

The reason for the long period between shut-down and complete decommissioning is that many radiation-contaminated components have to be dismantled and cleaned at great expense before they can be disposed of. And a nuclear power plant is big: at the Greifswald nuclear power plant, for example, 1.8 million metric tons of building material must be disposed of. The complex planning of shutdown and dismantling can be made easier by using a cutting-edge digital tool: Building Information Modeling (in short: BIM). This refers to a method of networked collaboration that brings together all relevant data in a model, enabling processes, products and participants to be digitally networked. In specific terms, this means that before the first stone is turned during dismantling, a digital model of the actual power plant and the technical equipment is constructed. ‘This model has long since included not just the geometric data, but also all the information on materials and fire control systems, for example,’ explained Peter Liebsch, Associate Partner at Drees & Sommer Group and expert for digital planning. This creates a digital twin with a depth of information down to the smallest detail.

High level of safety despite radiation contamination

All scheduling, (de)construction, material flow and logistics processes can then be simulated with the aid of this digital building model. Ideally, the model would be cloud-based, making it accessible to all project participants from any location. When BIM is used in planning the dismantling of a nuclear power plant, the entire power plant is first scanned with the appropriate equipment. ‘In areas that are inaccessible due to high radiation contamination, robots are used for this purpose. It is also possible to make measurements of things such as the contamination of individual areas with radioactivity, asbestos or other hazardous materials,’ Peter Liebsch continued. This method creates a faithful, virtual model of the power plant, including a contaminant register, which accurately represents the actual condition down to a few centimeters. In this model, the team plans the dismantling process and logistics, and adds critical information to it.

This procedure may sound time-consuming at first, because enhancing the digital twin with all the necessary data naturally increases the time and effort initially required at the preparation stage. But it does mean that discrepancies are not first noticed during the dismantling process and at the construction logistics stage, where they could result in expensive delays. Instead, the digital model is used to check for conflicts and consistency, ensuring that the deconstruction process runs smoothly. In addition, several variants of the demolition planning can be run through the BIM model and compared with each other, both with regard to scheduling and costs.

All the cogs mesh together

BIM also brings several major advantages in relation to the practical processes involved in dismantling. Firstly, occupational safety is increased for every individual who will later work on the plant. After all, you can take a virtual walk through the power plant and, by doing so, protect yourself from unpleasant surprises in reality. In the interests of occupational health and safety together with radiation protection, this reduces the time-consuming procedure of passing through air-lock systems to get to the hot zone. Secondly, the dimensions generated from the BIM model can be used for precisely scheduled demolition planning. They are also useful for detailed tendering, work preparation and logistics, including complete verification management for surveyors and official bodies. The dismantling process is much faster as a result, because all the cogs mesh together. And then it will not be long before nuclear energy in Germany really is a thing of the past – and in those places where reactor domes still tower up today, only green meadows will remain.

More Press releases

Social Media Wall

Have you followed us on LinkedIn and Instagram yet? This is where you'll find the content that we've shared most recently on our company channel. 

 

 

Current publications

Explore an overview or discover interesting details: Here you can find our latest published material, covering a range of topics.

Sustainability Report 2024

You can download our Sustainability Report 2024 here.

Download

Sustainability Report 2023

Forward-looking sustainability: Drees & Sommer is committed to sustainable corporate development that reconciles long-term economic success with ecological and social goals.      

Download

INNOVATION SCOUTING REPORT

On the trail of innovation: Find out more about the most important technology trends for the construction and real estate industry.

Download

Dossier

The future lies in existing buildings: existing properties offer huge potential not only economically, but also ecologically and functionally.

Download

Futureproofs

Looking back and looking ahead: Drees & Sommer Group business figures, statements and forward-looking topics and projects.

Download

Trend Study 2024

Corporate Real Estate Management - Digitalization and sustainability

Download

Digital Transformation Study

Digital Transformation in the Construction and Real Estate Industry: A Central European Perspective

Download

Drees & Sommer Logo

Download
Teaser Drees & Sommer Logos
Symbol Podcast

BLUE WAVES: The podcast for the world of construction and real estate

This is the Drees & Sommer podcast that explains more about the fascinating world of buildings, infrastructure, industry and urban development. Whether you're an industry insider or just curious about the world around us, Blue Waves provides insights into the real-estate industry for everyone. We discuss the topics that affect all of us.

 

this way

Events

Drees & Sommer uses various event platforms (real, digital or hybrid) to engage in dialog with customers and business partners.

Learn more
Teaser Event