Welcome to our Shared Content Center! This is where you will find news, current developments and interesting stories about our company and the topics that keep driving us forward. We share information here, about our projects, innovations and events, in a variety of formats, such as blog posts, press releases and files. If you want to keep yourself updated, you're in the right place. 

News

Latest First: In our news articles, you’ll find everything we currently have to report.

Press

Coal Gives Way to Rail: a New Maintenance and Repair Workshop for ICE 4 Trains

The new plant in Cottbus – the most modern maintenance and repair workshop of Deutsche Bahn. © GrandeMedia

Cottbus, Germany, July 30, 2025. In an area previously dominated by lignite mining, German railroad operator Deutsche Bahn (DB) is now building its most advanced repair and maintenance workshop for ICE 4 trains. Two bays with a total of six tracks and one painting line will be available for maintenance of the high-speed trains. Stuttgart-based Drees & Sommer SE specializes in construction, real estate and infrastructure consulting. The company’s team of experts provides advice on project management and cost and schedule controls issues.

Deutsche Bahn wants to invest around twelve billion euros in extending its long-distance rail network by 2030. This will increase its ICE fleet to 450 trains. The delivery of the last completed ICE 4 train, in March 2024, was a milestone on this journey. The trains in the brand-new fleet have to be serviced every 1.65 million kilometers – a distance covered in as little as around three to four years. To ensure that the trains are available to travelers again as quickly as possible, the new workshop was specially designed for this type of ICE train.

Workshop Already Operating at Full Capacity

The project’s first successes are evident in Bay 2. The 445-meter-long bay has been in operation since January 2024, and entire ICE 4 trains can be serviced here on two tracks. This makes time-consuming work such as switching the trains unnecessary. In this bay, staff members are relieved of work thanks to efficient and simplified processes because the use of state-of-the-art technology and automation speeds up maintenance operations.

Completion of Bay 1 is scheduled for 2026: The hall will offer four tracks (with a length of 500 meters and a width of 100 meters) and an automated painting line. Also under construction are a number of ancillary workshops, individual work platforms and an administration and staff social building. One of the special features: the new warehouse benefits from an automated box system in which goods and spare parts will be packed into standardized crates and stacked in a confined space. Several robots will travel across the grid on tracks, retrieve the desired crate at the touch of a button and take it to a work station, saving time and space.

The Rail Partnership Model

Deutsche Bahn is relying on a contract model that is completely new for realizing a complex infrastructure project of this scale. The Rail Partnership Model has been jointly developed by Deutsche Bahn, the Technical University of Berlin (TU Berlin) and the German Construction Confederation (ZDB). The integrated project delivery (IPD) method is characterized by a multi-party contract that is signed by all participating companies. Hence, all project partners are involved at an early stage and together share responsibility for the project. This results in a best-for-project principle: because opportunities and risks are shared equally, all teams pull together. This approach not only encourages collaboration, but it also ensures transparent processes and enables communication between equal partners.

Using Lean Planning to Achieve the Goal Quickly

Planning and implementation of a large-scale infrastructure project have to be learnt – they require precise coordination of schedules and deadlines, quality requirements, staff teams and resources. For example, when specific prefabricated components are delivered too late, the site manager has to act and respond quickly. Drees & Sommer applies lean construction management (LCM) techniques in order to enhance overall transparency and to streamline workflows and coordination processes.

The LCM approach is integrated into all project phases of the construction of the new ICE maintenance and repair workshop in Cottbus, from design and planning through site management to commissioning. Stefan Berger, project manager at Drees & Sommer, explains: “Firstly, we carry out an overall process analysis, and then the strategy and project sequence are planned in detail. Subsequently, we break down the whole construction process into subprojects and allocate the required resources. With the help of defined stability criteria ,we ensure at any time that all deadlines are met. So, all project participants can keep track of the progress of the project.“

Infrastructure Projects Are Becoming More Complex

Efficient processes are needed to manage today’s large-scale infrastructure projects due to their complexity and dynamics. Integrated project management (IPM), in conjunction with lean construction management, helps in keeping an overview of the project at any time: How is the project progressing? Are there any problems? Do we need to change something in our schedule? Drees & Sommer’s team of experts relies on digital planning tools. “LCM Digital enables us to visualize the progress of a project. This overview enables any deviation from the plan to be identified early so that the project can be brought back on course,” says Stefan Berger and adds: “In addition, resources – such as staffing or building materials and equipment – can be managed in a targeted and efficient manner in this way.”

More News

Blog posts

Get new insights into the work of Drees & Sommer and learn more about current topics, projects and trends.

Press

Coal Gives Way to Rail: a New Maintenance and Repair Workshop for ICE 4 Trains

The new plant in Cottbus – the most modern maintenance and repair workshop of Deutsche Bahn. © GrandeMedia

Cottbus, Germany, July 30, 2025. In an area previously dominated by lignite mining, German railroad operator Deutsche Bahn (DB) is now building its most advanced repair and maintenance workshop for ICE 4 trains. Two bays with a total of six tracks and one painting line will be available for maintenance of the high-speed trains. Stuttgart-based Drees & Sommer SE specializes in construction, real estate and infrastructure consulting. The company’s team of experts provides advice on project management and cost and schedule controls issues.

Deutsche Bahn wants to invest around twelve billion euros in extending its long-distance rail network by 2030. This will increase its ICE fleet to 450 trains. The delivery of the last completed ICE 4 train, in March 2024, was a milestone on this journey. The trains in the brand-new fleet have to be serviced every 1.65 million kilometers – a distance covered in as little as around three to four years. To ensure that the trains are available to travelers again as quickly as possible, the new workshop was specially designed for this type of ICE train.

Workshop Already Operating at Full Capacity

The project’s first successes are evident in Bay 2. The 445-meter-long bay has been in operation since January 2024, and entire ICE 4 trains can be serviced here on two tracks. This makes time-consuming work such as switching the trains unnecessary. In this bay, staff members are relieved of work thanks to efficient and simplified processes because the use of state-of-the-art technology and automation speeds up maintenance operations.

Completion of Bay 1 is scheduled for 2026: The hall will offer four tracks (with a length of 500 meters and a width of 100 meters) and an automated painting line. Also under construction are a number of ancillary workshops, individual work platforms and an administration and staff social building. One of the special features: the new warehouse benefits from an automated box system in which goods and spare parts will be packed into standardized crates and stacked in a confined space. Several robots will travel across the grid on tracks, retrieve the desired crate at the touch of a button and take it to a work station, saving time and space.

The Rail Partnership Model

Deutsche Bahn is relying on a contract model that is completely new for realizing a complex infrastructure project of this scale. The Rail Partnership Model has been jointly developed by Deutsche Bahn, the Technical University of Berlin (TU Berlin) and the German Construction Confederation (ZDB). The integrated project delivery (IPD) method is characterized by a multi-party contract that is signed by all participating companies. Hence, all project partners are involved at an early stage and together share responsibility for the project. This results in a best-for-project principle: because opportunities and risks are shared equally, all teams pull together. This approach not only encourages collaboration, but it also ensures transparent processes and enables communication between equal partners.

Using Lean Planning to Achieve the Goal Quickly

Planning and implementation of a large-scale infrastructure project have to be learnt – they require precise coordination of schedules and deadlines, quality requirements, staff teams and resources. For example, when specific prefabricated components are delivered too late, the site manager has to act and respond quickly. Drees & Sommer applies lean construction management (LCM) techniques in order to enhance overall transparency and to streamline workflows and coordination processes.

The LCM approach is integrated into all project phases of the construction of the new ICE maintenance and repair workshop in Cottbus, from design and planning through site management to commissioning. Stefan Berger, project manager at Drees & Sommer, explains: “Firstly, we carry out an overall process analysis, and then the strategy and project sequence are planned in detail. Subsequently, we break down the whole construction process into subprojects and allocate the required resources. With the help of defined stability criteria ,we ensure at any time that all deadlines are met. So, all project participants can keep track of the progress of the project.“

Infrastructure Projects Are Becoming More Complex

Efficient processes are needed to manage today’s large-scale infrastructure projects due to their complexity and dynamics. Integrated project management (IPM), in conjunction with lean construction management, helps in keeping an overview of the project at any time: How is the project progressing? Are there any problems? Do we need to change something in our schedule? Drees & Sommer’s team of experts relies on digital planning tools. “LCM Digital enables us to visualize the progress of a project. This overview enables any deviation from the plan to be identified early so that the project can be brought back on course,” says Stefan Berger and adds: “In addition, resources – such as staffing or building materials and equipment – can be managed in a targeted and efficient manner in this way.”

Dreso-Blog

Press Releases

Find out more about the latest developments and exciting news from our company in our current press releases.

Press

Coal Gives Way to Rail: a New Maintenance and Repair Workshop for ICE 4 Trains

The new plant in Cottbus – the most modern maintenance and repair workshop of Deutsche Bahn. © GrandeMedia

Cottbus, Germany, July 30, 2025. In an area previously dominated by lignite mining, German railroad operator Deutsche Bahn (DB) is now building its most advanced repair and maintenance workshop for ICE 4 trains. Two bays with a total of six tracks and one painting line will be available for maintenance of the high-speed trains. Stuttgart-based Drees & Sommer SE specializes in construction, real estate and infrastructure consulting. The company’s team of experts provides advice on project management and cost and schedule controls issues.

Deutsche Bahn wants to invest around twelve billion euros in extending its long-distance rail network by 2030. This will increase its ICE fleet to 450 trains. The delivery of the last completed ICE 4 train, in March 2024, was a milestone on this journey. The trains in the brand-new fleet have to be serviced every 1.65 million kilometers – a distance covered in as little as around three to four years. To ensure that the trains are available to travelers again as quickly as possible, the new workshop was specially designed for this type of ICE train.

Workshop Already Operating at Full Capacity

The project’s first successes are evident in Bay 2. The 445-meter-long bay has been in operation since January 2024, and entire ICE 4 trains can be serviced here on two tracks. This makes time-consuming work such as switching the trains unnecessary. In this bay, staff members are relieved of work thanks to efficient and simplified processes because the use of state-of-the-art technology and automation speeds up maintenance operations.

Completion of Bay 1 is scheduled for 2026: The hall will offer four tracks (with a length of 500 meters and a width of 100 meters) and an automated painting line. Also under construction are a number of ancillary workshops, individual work platforms and an administration and staff social building. One of the special features: the new warehouse benefits from an automated box system in which goods and spare parts will be packed into standardized crates and stacked in a confined space. Several robots will travel across the grid on tracks, retrieve the desired crate at the touch of a button and take it to a work station, saving time and space.

The Rail Partnership Model

Deutsche Bahn is relying on a contract model that is completely new for realizing a complex infrastructure project of this scale. The Rail Partnership Model has been jointly developed by Deutsche Bahn, the Technical University of Berlin (TU Berlin) and the German Construction Confederation (ZDB). The integrated project delivery (IPD) method is characterized by a multi-party contract that is signed by all participating companies. Hence, all project partners are involved at an early stage and together share responsibility for the project. This results in a best-for-project principle: because opportunities and risks are shared equally, all teams pull together. This approach not only encourages collaboration, but it also ensures transparent processes and enables communication between equal partners.

Using Lean Planning to Achieve the Goal Quickly

Planning and implementation of a large-scale infrastructure project have to be learnt – they require precise coordination of schedules and deadlines, quality requirements, staff teams and resources. For example, when specific prefabricated components are delivered too late, the site manager has to act and respond quickly. Drees & Sommer applies lean construction management (LCM) techniques in order to enhance overall transparency and to streamline workflows and coordination processes.

The LCM approach is integrated into all project phases of the construction of the new ICE maintenance and repair workshop in Cottbus, from design and planning through site management to commissioning. Stefan Berger, project manager at Drees & Sommer, explains: “Firstly, we carry out an overall process analysis, and then the strategy and project sequence are planned in detail. Subsequently, we break down the whole construction process into subprojects and allocate the required resources. With the help of defined stability criteria ,we ensure at any time that all deadlines are met. So, all project participants can keep track of the progress of the project.“

Infrastructure Projects Are Becoming More Complex

Efficient processes are needed to manage today’s large-scale infrastructure projects due to their complexity and dynamics. Integrated project management (IPM), in conjunction with lean construction management, helps in keeping an overview of the project at any time: How is the project progressing? Are there any problems? Do we need to change something in our schedule? Drees & Sommer’s team of experts relies on digital planning tools. “LCM Digital enables us to visualize the progress of a project. This overview enables any deviation from the plan to be identified early so that the project can be brought back on course,” says Stefan Berger and adds: “In addition, resources – such as staffing or building materials and equipment – can be managed in a targeted and efficient manner in this way.”

More Press releases

Social Media Wall

Have you followed us on LinkedIn and Instagram yet? This is where you'll find the content that we've shared most recently on our company channel. 

 

 

Current publications

Explore an overview or discover interesting details: Here you can find our latest published material, covering a range of topics.

Sustainability Report 2024

You can download our Sustainability Report 2024 here.

Download

Sustainability Report 2023

Forward-looking sustainability: Drees & Sommer is committed to sustainable corporate development that reconciles long-term economic success with ecological and social goals.      

Download

INNOVATION SCOUTING REPORT

On the trail of innovation: Find out more about the most important technology trends for the construction and real estate industry.

Download

Dossier

The future lies in existing buildings: existing properties offer huge potential not only economically, but also ecologically and functionally.

Download

Futureproofs

Looking back and looking ahead: Drees & Sommer Group business figures, statements and forward-looking topics and projects.

Download

Trend Study 2024

Corporate Real Estate Management - Digitalization and sustainability

Download

Digital Transformation Study

Digital Transformation in the Construction and Real Estate Industry: A Central European Perspective

Download

Drees & Sommer Logo

Download
Teaser Drees & Sommer Logos
Symbol Podcast

BLUE WAVES: The podcast for the world of construction and real estate

This is the Drees & Sommer podcast that explains more about the fascinating world of buildings, infrastructure, industry and urban development. Whether you're an industry insider or just curious about the world around us, Blue Waves provides insights into the real-estate industry for everyone. We discuss the topics that affect all of us.

 

this way

Events

Drees & Sommer uses various event platforms (real, digital or hybrid) to engage in dialog with customers and business partners.

Learn more
Teaser Event