© Robert Herschler
Bâtiments de santé et soins
Hôpital Kirchberg
Client
Hôpitaux Robert Schumann S.A.
Location
2540 Luxembourg
Architect
Incopa Plan GmbH
Project duration
January 2013 to April 2017
Net costs
19 Mio. €
Gross floor area
4.908 m²
Gross volume capacity
19.905 m³
Drees & Sommer supported this new building at the site of the "Hôpital Kirchberg" clinic with project management. A parking lot, a day clinic, operating rooms, doctors' surgeries and a maternity ward (with upscale equipment) were created. During construction, the project was adapted to new requirements and the construction works were coordinated and adapted accordingly.
Added value
- Respect of the project budget
- Adjustment of planning in the ongoing construction process
- The changed requirements of the customer were taken into account
Services
Project Management