Bâtiments de santé et soins

Hôpital Kirchberg

© Robert Herschler
Client

Hôpitaux Robert Schumann S.A.

Location

2540 Luxembourg

Architect

Incopa Plan GmbH

Project duration

January 2013 to April 2017

Net costs

19 Mio. €

Gross floor area

4.908 m²

Gross volume capacity

19.905 m³

Drees & Sommer supported this new building at the site of the "Hôpital Kirchberg" clinic with project management. A parking lot, a day clinic, operating rooms, doctors' surgeries and a maternity ward (with upscale equipment) were created. During construction, the project was adapted to new requirements and the construction works were coordinated and adapted accordingly.

Added value

  • Respect of the project budget
  • Adjustment of planning in the ongoing construction process
  • The changed requirements of the customer were taken into account

Services

Project Management